Your Building Process

At BrightEdge, we believe that building process should be transparent and enjoyable journey. The BrightEdge process takes guesswork out of building your new home.

This marks the start of journey and we start presenting you the design options for your dream home. Your Sales Consultant will provide you with information and will take the time to understand your needs.

  • You will be presented with a sales estimate, containing options you have selected for your home.
  • Client pays initial Non Refundable deposit. This deposit will secure a site start allocation and Inclusions, subject to signing contracts within 90 days.
    • $1000 for Standard plans
    • $3000 for Custom plans

At this stage, we prepare the tender document based on the sales estimate. The preliminary drawings are drafted to capture your requirements.

  • Your Sales Consultant will present you through the drawings and answer any questions you may have.
  • Your Sales Consultant will present you tender documents and answer any questions you may have.
  • Client to double check all the design requirements are captured on the drawings, Client to make sure the drawings are properly explained by consultant.
  • Once completed you will also need to pay a secondary Non-refundable deposit, to confirms that you wish to proceed to the next step.

Please Note: No further structural changes will be accepted after this stage, and facade must be nominated. Please Note: Final Facade and House design must be confirmed at this stage. A $500 fee will apply after this point in the process.

This is where everything comes to life. We present your building working drawings for you to look at and sign off.

  • Your Sales Consultant will present you through the drawings and answer any questions you may have.
  • Client to review the drawings making sure all the requirements are captured.
  • Client to make sure that all the drawings are properly explained by sales consultant.

This is one of the most exciting steps, where you will get to choose the styling of your home, both inside and out.

During the entire appointment, our professional colour consultant will help you to create your vision.

Please ensure all structural changes are finalised with your New Home Consultant prior to this appointment and your facade has been selected.

  • Allow approximately 4 hours for this appointment.

BrightEdge Homes to provide HIA Plain English Building Contract and associated documents, including preliminary documents, tender, colour selection, builders specifications and contract drawings to customer in advance for client to review prior to contract appointment.

  • BrightEdge Homes to apply for building permit and Developer’s approval (if applicable)
  • Balance of 5% of contract value is due.
  • Please Note: No further changes will be accepted after this stage.

Summary of Payment Process
All payments are nominated in the HIA Building Contract and are as follows:

  • Deposit 5% (less deposit already paid) 
  • Base 15%
  • Frame 25%
  • Lockup 25%
  • Fix 20%
  • Completion 10%

Introductory Call
A member of our team from head office will call you to introduce themselves and your building supervisor. They will be your point of contact throughout your construction journey and will be able to answer any questions you have. Your Customer Service Specialist will provide you with regular update on how your new home construction is progressing. BrightEdge Homes to send a letter confirming construction has commenced.

Base Stage
Your block of land will be prepped and ready to build on, with temporary fencing installed, site excavation, and underground connections laid. Base stage is complete once the concrete slab is poured. 

Reminder Upon completion of base stage, a 15% progress payment is due within 14 days.

Client is welcome to inspect this stage with the Construction Supervisor prior to making progress payment, as long as the payment is made within14 days of the invoice date.

Frame Stage
This is when your home really starts to come to life. All walls are marked out in accordance with your final drawings, and construction of wall, windows & door frames, and roof trusses begin. Frame stage is complete once the frame is completed, inspected, and approved by a qualified Building Surveyor.

Reminder Upon completion of base stage, a 25% progress payment is due within 14 days

Lock up Stage 

This is a significant milestone in construction. Brickwork, wall cladding, roofing, and insulation are all installed. Temporary external doors may be hung and fixed into position in order to ensure the security of your home.

Reminder Upon completion of lock up stage, a 25% progress payment

Client is welcome to inspect this stage with the Construction Supervisor prior to making progress payment, as long as the payment is made within14 days of the invoice date.

Fixing Stage
This is where we begin fixing everything into position. We will complete all internal plaster, architraves/skirtings, cabinets and cupboards to your kitchen.
You will see your colour selections come to life. Whilst we paint your home, we will install tiles, benchtops, shower screens, mirrors, and door furniture. We will fit off all plumbing.

Reminder Upon completion of fixing stage, a 20% progress payment is due within 14 days

Practical Completion Inspection (PCI)
At this stage, your Construction Supervisor will arrange for your new home presentation. This appointment is a chance for your Construction Supervisor to present your home to you, pointing out all of the features. A settlement date will also be confirmed with you at this appointment.

A thorough quality assurance inspection is conducted on the home by a dedicated Quality Assurance Team.

A Builder Surveyor will complete the final inspection and issue a certificate of occupancy which is then forwarded to the client.

Client Liaison Executive to forward on the certificate of occupancy once available. Client to forward certificate of occupancy to financial institution (if applicable) to release final payment.

Settlement generally takes place 7 to 14 days after your PCI Fifth and Final Progress Payment is due at settlement – 10% of contract value plus any unpaid variations.

Please Note: A bank cheque or direct deposit is required for final payment. If direct deposit is made, please ensure transfer is made at least two clear business days prior to settlement.

Handover
Congratulations! Your new Home has been completed and is ready for you to move in.

On the day of settlement the Construction Supervisor will conduct an on-site handover. Appliances will be installed at an agreed time after settlement has taken place.

Client is to make final payment on the day of settlement. This amount includes the last stage payment and any unpaid variations. Once paid, the keys and settlement pack will be presented.

Now you’re in your brand new home, it’s time to commence the aftercare program. Once you have taken possession of your new home, your builder is obliged to perform routine maintenance and carry out any adjustments caused from settlement.

The industry standard for this maintenance period is thirteen weeks, however BrightEdge Homes offer an extended period of six months from the settlement date of your home. Our Home Assurance Team will contact you at approximately eleven months after Settlement to book in a suitable time to visit your home.

Should you wish to have your maintenance inspection brought forward, please contact the aftercare Department.